Changing an Implement Action Plan Due Date

The implement action plan due date can be changed from the Implement Action Plan task.

  1. From the Implement Action Plan task, click the Change Due Date link.
    Result: The Change Implementation Due Date window is displayed.
  1. Enter a new date in the Implement Action Plan Due Date field.
  2. Enter a reason for the change in the Reason field.
  3. Click the Sign-off button.
    Result: The Sign-off window is displayed.
  4. Enter your user ID and password and then click the Sign-off button.
    Result: The due date is changed.